Lebanon Middle School Lebanon NH

Lebanon Middle School Lebanon NH
Williston, VT Kelley Bros – Williston, VT provided a complete furnished and installed turnkey solution for this project including an RS2 Access Control System. Office provided the following products: Custom Hollow Metal Doors and Frames: Curries Mfg. Co. Wood Doors: Eggers Industries Locksets: Sargent 8200 Series Mortise Locks and Harmony Access Control Lock Access Control System: RS2 Door Closers and Door Operators – Sargent 350 series Exit Devices: Sargent 80 Series Flat Good and Auxiliary Hardware: Rockwood Mfg. Co Weather-stripping, Thresholds and Door Bottoms: Pemko Products
  • Project Type: School
  • Architect: Banwell Architects – Lebanon, NH
  • General Contractor: Trumbull Nelson Construction Co – Hanover, NH
  • Awards: NA
  • End User: NA
  • Size: NA

Project Story

Trumbull-Nelson completed work on the new, 109,000 square foot Lebanon Middle School (LMS). The Project broke ground in October 2010, and was completed on budget and on schedule in April 2012. The School accommodates up to 600 students.

The school was a New England Collaborative for High Performance Schools (NECHPS) project. Features of the design include: 30 classrooms, science labs, library and media center, computer lab, art, instrumental and chorus rooms, cafeteria, nurse’s office, administrative offices, gymnasium, and biomass heating system.

AHC AHC
CDC CDC
AHC AHC
Our Locations

View our current locations to learn more about how we can best serve you.

  • Alabama
  • New Hampshire
  • Arizona
  • New Jersey
  • Connecticut
  • New York
  • Georgia
  • Ohio
  • Indiana
  • Pennsylvania
  • Maine
  • Texas
  • Massachusetts
  • Vermont
footer logo
Our Locations

View our current locations to learn more about how we can best serve you.

  • Alabama
  • New Hampshire
  • Arizona
  • New Jersey
  • Connecticut
  • New York
  • Georgia
  • Ohio
  • Indiana
  • Pennsylvania
  • Maine
  • Texas
  • Massachusetts
  • Vermont